Note about using up all available forgings for the new type flywheel and clutch, with a 3-4 week delay for new stock.

Identifier  ExFiles\Box 107\1\  scan0254
Date  3rd January 1935
  
x7960

W/S - C. from Hs{Lord Ernest Hives - Chair}/Rm.{William Robotham - Chief Engineer}

Hs{Lord Ernest Hives - Chair}/Rm.{William Robotham - Chief Engineer}19/KW.3.1.35.

GZU-24.

C23/C.31.12.34.

We found that we had used up all the forgings available for the new type flywheel and clutch. We have therefore had to put some more in hand, and it will be three or four weeks before these are ready.

Hs{Lord Ernest Hives - Chair}/Rm.{William Robotham - Chief Engineer}
  
  