Delayed release of parts details for the 40/50 HP Chassis, N2 Series.


Identifier  ExFiles\Box 142\2\  scan0128
Date  30th September 1930
  
X4554.

To BY. {R.W. Bailey - Chief Engineer} from ROY. {Mr H. Royce - Buyer}
c. to Wor. {Arthur Wormald - General Works Manager}
c. to Hs. {Lord Ernest Hives - Chair}
c. to SPT.

ROY {Mr H. Royce - Buyer} 5/MG30.9.30

----------------

40/50 HP. Chassis - N2 Series

BY7/N29.9.30 - Thank you for the details re above. It is noted many of the details were to be released yesterday, the result being, 8 weeks from now Chassis embodying such details are due to Road Test - which I think we must all agree gives everyone very short notice as far as Production is concerned.

x. As far as Radiator Section 5250 is concerned, your Memo. BY {R.W. Bailey - Chief Engineer} /CGS2/IG24.9.30 releasing same has not yet reached the O.O. - presumably it is in the O.P Dept., and we are urging them for same.

Re Carburetter and Controls, Sections 5030 and 5240. The/old parts admittedly were released for the first 50 sets, but these were included in our Shortage List, as we are not authorised to release any of same for the L.H. Chassis; i.e., although we have authority for such Carburetter details for/the first 50 R.H.Chassis, there is nothing whatever yet released for the L.H.Chassis.

ROY. {Mr H. Royce - Buyer}

x Series to hand

RECEIVED
OCT 1 1930
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙