Comparison of completion dates for sports bodies from coachbuilders Barker, Hooper, and Jarvis.
Identifier | ExFiles\Box 71\1\ scan0368 | |
Date | 28th November 1927 | |
DATES FOR THE COMPLETION OF THE SPORTS BODIES. | | BARKER. | HOOPER. | JARVIS | |---|---|---|---| | Would like to receive the chassis in | 10 days | 2 weeks | 7 days | | Will be held up for the chassis in. | 3 weeks | 3 weeks | month | | If the chassis is received in 10 days delivery in | 7 weeks | 4 weeks | 7 weeks | | Chassis received as late as possible, delivery in | 7 weeks | 5 weeks | 8 weeks | | Christmas Holiday. | week | 3 days | 3 1/2 days | | How far advanced. | Just begun to cut up templates for mill week. | Work been in the mill almost a week. | Most of stuff is milled. | All the above times date from Monday November 28th. 1927. and include the Christmas Holiday. | ||