Comparison of completion dates for sports bodies from coachbuilders Barker, Hooper, and Jarvis.

Identifier  ExFiles\Box 71\1\  scan0368
Date  28th November 1927
  
DATES FOR THE COMPLETION OF THE SPORTS BODIES.

| | BARKER. | HOOPER. | JARVIS |
|---|---|---|---|
| Would like to receive the chassis in | 10 days | 2 weeks | 7 days |
| Will be held up for the chassis in. | 3 weeks | 3 weeks | month |
| If the chassis is received in 10 days delivery in | 7 weeks | 4 weeks | 7 weeks |
| Chassis received as late as possible, delivery in | 7 weeks | 5 weeks | 8 weeks |
| Christmas Holiday. | week | 3 days | 3 1/2 days |
| How far advanced. | Just begun to cut up templates for mill week. | Work been in the mill almost a week. | Most of stuff is milled. |

All the above times date from Monday November 28th. 1927.
and include the Christmas Holiday.
  
  