Rolls-Royce Archives
         « Prev  Box Series  Next »        

From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Production hold-up on the Bentley V chassis due to a gearbox change and its impact on delivery schedules.

Identifier  ExFiles\Box 97\2\  scan0018
Date  2nd February 1939
  
HOD

To BY.{R.W. Bailey - Chief Engineer} Rm.{William Robotham - Chief Engineer} RHC.{R. H. Coverley - Production Engineer} Roy{Sir Henry Royce}/Les.{Ivan A. Leslie} BY.{R.W. Bailey - Chief Engineer} & BY/NS.{Norman Scott} From RHC{R. H. Coverley - Production Engineer}/G.Mc.

BENTLEY V.{VIENNA}

No mention is made in the minutes of the conference held 25.1.39. that the decision, "to hold up all parts which were affected by the change of Gearbox" would make it impossible to deliver the Bentley V.{VIENNA} Chassis to Sales by July.

When this point was raised, Rm.{William Robotham - Chief Engineer} referred to a memo' in which he had stated the Release would be given in March for Production, the question of Experimental Production being overlooked. This should have followed Wraith practice.

The position as BY.{R.W. Bailey - Chief Engineer} pointed out would be somewhat relieved as the Coachbuilders were proceeding to build the Bodies at the same time as the Chassis were going forward, leaving only the Fitting and Final Finishing to be completed after receipt of the Chassis.

RHC{R. H. Coverley - Production Engineer}/G.Mc.
  
  


Copyright Sustain 2025, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙