From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Outlining requirements for a weekly progress report on the 'SS' and Schneider Cup 'R' engine projects.

Identifier  ExFiles\Box 65a\2\  scan0252
Date  13th March 1929
  
To BY.{R.W. Bailey - Chief Engineer}
c. Hs.{Lord Ernest Hives - Chair}
c. RHC.{R. H. Coverley - Production Engineer}
X7770
SECRET.
Wor{Arthur Wormald - General Works Manager}4/H.13.3.29.

re "SS{S. Smith}" and the Question of Production,
and
Schneider Cup "R" Engine.X4674

Sg.{Arthur F. Sidgreaves - MD} has asked me to let him have a report weekly of the progress of these items as under :-

"SS{S. Smith}" and the Question of Production.

1. The items which are not yet completed from a Drawing Office or experimental point of view.
2. The date on which they must be completed to prevent the possibility of delay in your production.
3. Information from the people concerned as to what date they will be completed by.{R.W. Bailey - Chief Engineer}
4. What progress has been made with such items since the last report.
  
  