Letter to Mr. Healey concerning production rates, equipment arrival from the States, and operational timelines.

Identifier  ExFiles\Box 176\3\  img193
Date  10th August 1940
  
Em.S/L.

T.J.Healey, Esq.,
RCF.
Lirgin Meadows,
LOUTHMAUTH.

10.8.40.

Dear Mr. Healey,

Thank you for your letter of the 8th. August.

We are very much obliged to you for the information it contains.

We trust that it will be possible for you to carry on with twenty per month for the completion of the first sixty.

If possible, we should like production to continue at the rate of four per week until our own equipment arrives from the States and can be put into operation.

We shall be fortunate if those machines are running by January 1st. 1941.

Yours sincerely,
  
  