Production schedule and material order dates for the Phantom III Chassis - D.Series.


Identifier  ExFiles\Box 142\2\  scan0401
Date  15th February 1937
  
ROY {Mr H. Royce - Buyer} 8/A 15.2.37

PHANTOM III CHASSIS - D.SERIES

D-A. {Mr Adams} 601-700
D-B. 701-800

Number of Chassis in Series ....................... 200
Proposed Output ................................... 12 per week to end of July
Authority to proceed .............................. Sg {Arthur F. Sidgreaves - MD} 12/E1.2.37
Drawing Office to complete issue of instructions week ending ...................................... February 8th.1937

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:

Class D - Forging Bars & Billets .................... Feb. 13th.1937
Class C - Finished Bars, Sheets, Strip &c.............. " 27th. "
Class B - Gear Box Gears .............................. " 13th. "
" - Forgings, Pressings &c ........................ " 20th. "
Class A - Finished Details ............................ Mar. 6th. "
Instruments ....................................... Mar. 6th. "

MATERIAL TO BE IN STORES:

First 50 Crankshafts .............................. Apr. 29th.1937
Class D - Forging Bars & Billets for Gear Box Gears... " 3rd. "
" - Other Forging Bars & Billets ................ " 10th. "
Class C - 100 Camshaft Bars, and Finished Bars 1-3/16" dia. and over ............................ May. 1st. "
" - All Finished Bars under 1-3/16" dia., Camshaft Sheet, Strip, Tubes etc................. " 8th. "
Class B - Forgings, Pressings &c....................... " 1st. "
Class A - Finished Pressings &c ..................... Jun. 5th. "
Instruments (12 sets per week) .................... " 5th. "

PRODUCTION CARDS TO BE ISSUED:

Gear Box Gear Blanks .............................. Apr. 10th.1937
First 50 Crankshaft Forgings ...................... May. 8th. "
(Afterwards at 15 per week)
Crankcase (Sec.5000) all details for machining ... May. 1st. "
Class D - Forging Bars & Billets for Gear Box Blanks.. Apr. 10th. "
" - Ditto for other RR. Forgings & Castings ..... May. 1st. "
Class C - 100 Camshaft Bars, and all Finished Bars 1-3/16" dia. and over ............................ May 15th. "
" - Smaller sizes, and balance of Camshafts, Strips, Sheets, Tubes, &c....................... May 22nd. "
Class B - Forgings, Pressings &c. and balance of Crankshafts .................................... May 15th. "
Class A - Finished Pressings &c ..................... June 19th. "
Instruments (12 sets per week) .................... July 3rd. "
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙