Held-up details and future improvements for the Bentley 'L' Series chassis.

Identifier  ExFiles\Box 142\2\  scan0392
Date  12th January 1937
  
EH/egh.
c. to RHC.{R. H. Coverley - Production Engineer}
c. to Rm.{William Robotham - Chief Engineer}

J 1200

ROY{Sir Henry Royce}/MS24/F.12.1.37.

BENTLEY CHASSIS - "L" SERIES MATERIAL.

With reference to the various details held up on the above series, the first chassis is due to test July 3rd, and if the Works are to continue output without break it is necessary we have instructions immediately for the various items held up, either new or old details.

Any necessary improvements can be brought in on the 101st chassis, which is due to test week ending September 11th, and the Order Office should have instructions to order such details not later than February 27th.

Roy{Sir Henry Royce}
  
  