Scheduling a conference to discuss advance estimates and routines for the Rationalised Chassis Programme.


Identifier  ExFiles\Box 148\2\  scan0232
Date  17th August 1939
  
1260

To By. {R.W. Bailey - Chief Engineer}
c. to Rm. {William Robotham - Chief Engineer}
c. to RHC. {R. H. Coverley - Production Engineer}
c. to RHC {R. H. Coverley - Production Engineer} /AML.
c. to RHC {R. H. Coverley - Production Engineer} /Wld/JF.
c. to Les. {Ivan A. Leslie}

By {R.W. Bailey - Chief Engineer} /NS. {Norman Scott} 10/JH.17.8.39.

Advance Estimates for Rationalised Chassis Programme.

We have been asked in the memo. RHC {R. H. Coverley - Production Engineer} /AML.1/MD.10.8.39. to keep the Rate Fixing Department up to date with information relating to the Rationalised Chassis.

As a temporary measure we have supplied RHC {R. H. Coverley - Production Engineer} /AML. with copies of the specifications that have been produced. We have also obtained prints of LOP's. that have not been instructed for production.

We propose to hold a conference with RHC {R. H. Coverley - Production Engineer} /Wld/JF. and RHC {R. H. Coverley - Production Engineer} /AML. to fix up the routine for future use.

The conference will take place at 10 o-clock on Friday 18th. in the writers office.

By {R.W. Bailey - Chief Engineer} /NS. {Norman Scott}
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙