Work schedule and parts request for a Chassis S/C Unit.

Identifier  ExFiles\Box 133\1\  scan0177
Date  15th March 1937
  
1129.
To HPS.{Horace Percy Smith - Experimental Factory Mgr}
c. to E/PSN.
Rm{William Robotham - Chief Engineer}/Ed.{J. L. Edwards}17/JH.15.3.37.
Chassis S/C Unit.
Running time for week ending 13th March 1937 15¼ hrs.
Fitting time " " " " 22¼ hrs.
Programme for week ending 20th March,1937.
Work to be done    time.
Power and detonation tests on No. 2 head (RS.{Sir Henry Royce's Secretary}314) deturbulated to Leo.5422.    1 day.
SHOP. Remove No.2 head and fit alum. head RS.{Sir Henry Royce's Secretary}315
Check power and detonation.    1 day.
Shop. Remove alum. head and fit deturbulated No.2 head with a .010" cerrujoint washer.
Power and disstohtion tests.    2 days.
SPARES.
We understand push rods RS.{Sir Henry Royce's Secretary}441 are now ready, these should be fitted as soon as possible.
We should be glad if you would urge the spare inlet valves EB.2026 as fast as possible, as the time waste in changing the valve with every change of cylinder head is considerable.
  
  