Estimate for the cost of new tools for the 'D' series chassis production.
Identifier | ExFiles\Box 171\2\ img311 | |
Date | 25th August 1935 | |
PART No. III STANDARDISATION of PARTS Ref. No. TC./1 Date 25.8.35 [X] Estimated cost of new tools £362. 0. 0. Could be brought on to production at the 1st. chassis in "D" series (without scrap). MATERIAL £ s d 33 8 1 LABOUR £ s d 22 16 8 CHARGES £ s d 58 1 1 TOTAL £ s d 114 5 10 INITIAL | DATE | REMARKS SC | 26.8.35 | Agreed .SE HS{Lord Ernest Hives - Chair} | | C | 28.8.35 | Agreed EW | | Agreed AQ | 28.8.35 | Agreed VB | 28.8.35 | Agreed .gb RHC{R. H. Coverley - Production Engineer} | 2.9.35 | Agreed .EHR MM | 2.9.35 | Agreed RM{William Robotham - Chief Engineer} | | Agreed | ||