Delay in receiving M.40 test rig parts from Lockheeds.


Identifier  ExFiles\Box 110\1\  scan0065
Date  24th March 1942
  
To Roy {Mr H. Royce - Buyer} /AES. from Rm {William Robotham - Chief Engineer} /MHR. {M. H. Rigby}

706
10000

Rm {William Robotham - Chief Engineer} /MHR. {M. H. Rigby} 2/ET.24.3.42.

M.40 - TEST RIG.
-----------------

We have not yet received the first set of M.40 parts from Lockheeds, and as we are not in a position to use them, we are therefore allowing Lockheeds to continue developing them until we are ready.

Rm {William Robotham - Chief Engineer} /MHR. {M. H. Rigby}
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).