The progress of Wraith II frames and fittings following a supplier visit.
| Identifier | ExFiles\Box 8\10\ 10-page035 | |
| Date | 27th November 1936 | |
| To Rm. {William Robotham - Chief Engineer} from HPS {Horace Percy Smith - Experimental Factory Mgr} /WSC. {W. S. Cassel} LOGG 627 HPS {Horace Percy Smith - Experimental Factory Mgr} /WSC. {W. S. Cassel} 13/BA.27.11.36. WRAITH II Frames & Fittings. Re: Visit to Messrs. Rubery Owen by W. Butterworth 26.11.36. The above firm are now in possession of all necessary pressing tools, and are making final alterations to the assembling jig. The promise of delivery of the 1st Frame (in SWG.14 .080 thick) is confirmed, not later than December 15th, and are trying, if possible to bring this date forward. HPS {Horace Percy Smith - Experimental Factory Mgr} /WSC. {W. S. Cassel} | ||
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).