Acquisition and production schedule for J.2 Series Chassis frames.


Identifier  ExFiles\Box 19\3\  Scan041
Date  20th February 1929
  
DY. {F R Danby} from ROY. {Mr H. Royce - Buyer} [struck through]
c. to Hs. {Lord Ernest Hives - Chair} [struck through]
c. to RHC {R. H. Coverley - Production Engineer} [struck through]
-----------------
x7772 [handwritten]
ROY {Mr H. Royce - Buyer} 7/MG20.2.29
-----------------
L.H.SS {S. Smith} - J.2 Series Chassis

BY16/G18.2.29 - We have bought 8 pairs hand smithed Frames in all, instructed by RHC {R. H. Coverley - Production Engineer} , and it is just possible one or more may be available now for Chassis. [handwritten note 'above']

Meantime Thompsons are proceeding all speed with the hand smithing of a further 4 Frames, and I am expecting the first 2 here in about 10 days time, the remaining 2 a week or so later.

ROY {Mr H. Royce - Buyer}
[signature]
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙