Minutes from a chassis conference meeting held on Tuesday 16th May 1939.


Identifier  ExFiles\Box 161a\3\  scan0167
Date  16th May 1939
  
1381

To HPS. {Horace Percy Smith - Experimental Factory Mgr} from HPS {Horace Percy Smith - Experimental Factory Mgr} /WSC. {W. S. Cassel}
c. Rm {William Robotham - Chief Engineer} Rm {William Robotham - Chief Engineer} /Swdl. {Len H. Swindell} RH. {R. Hollingworth}
c. LK. {L. King} AG. TB. WL.
c. FN. TT. CP.

HPS {Horace Percy Smith - Experimental Factory Mgr} /WSC. {W. S. Cassel} J/BA.17.5.39.

CHASSIS CONFERENCE HELD TUESDAY 16.5.39.

Personnel present: - RH. {R. Hollingworth} LK. {L. King} TB. AG. CP. FS. {F. Steele} FN. TP. WSC. {W. S. Cassel}

New Chassis Instructed.

10.B.V. This chassis is now on test, production type of Rear axle is to be fitted, also corks to the front hubs as shown on Arrgt. GB.4377.

11.B.V. The car now in the shop having been received back from Coachbuilders and is being completed to the specification.

12.B.V. This car was received back from the Coachbuilders late 16.5.39 we are proceeding to complete same to specification.

14.B.V. This chassis is still at the Coachbuilders in France having the body fitted and it is anticipated same will be back towards the end of this month. An all Helical Gear Box to be fitted, and a Rear Axle with 12 x 41 ratio gears and Alum Front Shock Dampers..

Remarks.

RH. {R. Hollingworth} stated that the production type of rear axle was to be completed by the 23rd.

B.80.No.3 Engine Unit will be ready for fitting to the chassis wednesday 17th. HL. is requested to give RH. {R. Hollingworth} a completion date for the 11 x 41 gears in S/ZNC. The car is being passed to test Thursday 18th.

FB.4873/4 Side Steering Levers. LK. {L. King} promised to complete by the 24th.
GB.4798 Hubs are promised for the 19th.
FB.4453/4 Tri.Levers " " " 21st.
The Rear Axle is " " " 21st.
Car to be passed to test on the 24th.

FB.4469 Steering Wheel.WSC. {W. S. Cassel} to see Roy {Mr H. Royce - Buyer} /Les re delive y.
FB.4871/4 Steering Levers will be completed on the 26th.
FB.4880/1 Triangular Levers will be completed on the 26th.
FB.4798 Front Hubs will be 26th.
FB.4387 Pendulum Levers will be completed on the 26th.
Rear Axle to be completed by the 26th.

continued.
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙