| Description | Date | Identifier | |
| Instruction to construct wooden shelves for material storage in Bumper House. | 8th May 1939 | Box 143 \ 1 scan0365 | |
| Request to have a blind fitted in an office due to excessive heat from the sun. | 11th May 1939 | Box 143 \ 1 scan0366 | |
| The purchase of a four-drawer filing cabinet. | 19th May 1939 | Box 143 \ 1 scan0367 | |
| The supply of a metal cupboard for test house No. 30. | 19th May 1939 | Box 143 \ 1 scan0368 | |
| Request for two handles for a drilling machine in the Bump House. | 7th Jun 1939 | Box 143 \ 1 scan0369 | |
| Specifications for a flexible coupling required for the No.5 Test House. | 21th Jun 1939 | Box 143 \ 1 scan0370 | |
| Request to replace doors at the Welfare Hall to allow for car access. | 27th Jun 1939 | Box 143 \ 1 scan0371 | |
| Requested modifications to a shock damper indicator rig. | 28th Jun 1939 | Box 143 \ 1 scan0372 | |
| Equipment estimate for completing piping, and fitting a Fan Guard and overflow Tank to No. 2 Test Bed. | 5th Jul 1939 | Box 143 \ 1 scan0373 | |
| Installation and costs of a chassis dynamometer in the garage. | 19th Jul 1939 | Box 143 \ 1 scan0374 | |
| Cost breakdown for fitting a 150 HP Electric Motor and torque convertor to the Chassis Dynamometer. | 24th Jul 1939 | Box 143 \ 1 scan0375 | |
| Equipment estimate for a coupling with torsional flexibility for Universal Bed No. 5 Test House. | 22th Mar 1939 | Box 143 \ 1 scan0376 | |
| Order for a commercial series art metal cupboard. | 23th Aug 1939 | Box 143 \ 1 scan0377 | |
| Equipment estimate for necessary repairs to an electric switch on a ramp in the Experimental Garage. | 26th Aug 1939 | Box 143 \ 1 scan0378 | |
| Equipment estimate for two engine erecting trestles of a turn-over type. | 8th Oct 1939 | Box 143 \ 1 scan0379 | |
| Equipment estimate for the repair of a bearing on the dynamo test rig in the Electrical Laboratory. | 10th Nov 1939 | Box 143 \ 1 scan0380 | |
| Request to obtain a high-pressure gauge and suction thermometer for the ammonia cold chamber plant in the experimental garage. | 14th Nov 1939 | Box 143 \ 1 scan0381 | |
| From Rm. to EJJ. forwarding a catalogue for Davy & United Engineering Co. Ltd. | 17th Nov 1939 | Box 143 \ 1 scan0382 | |
| Requesting the urgent completion and fitting of a flexible coupling for No.5 Test House. | 30th Nov 1939 | Box 143 \ 1 scan0383 | |
| Requesting an office desk and chair for Bump House. | 2nd Dec 1939 | Box 143 \ 1 scan0384 | |
| Request to order a Milners steel cupboard for filing purposes on the Aero Weight Analysis job. | 5th Dec 1939 | Box 143 \ 1 scan0385 | |
| The rig for testing Vulture auxiliary gearboxes, discussing the unavailability of a Wraith engine and the modification costs for a substitute. | 12th Dec 1939 | Box 143 \ 1 scan0386 | |
| Decision to supply an older, out-of-date unit instead of a new Wraith unit to avoid extravagance. | 14th Dec 1939 | Box 143 \ 1 scan0387 | |
| Instructing the pattern shop to make a stand based on an accompanying sketch for the experimental weight analysis section. | 13th Jan 1940 | Box 143 \ 1 scan0388 | |
| Equipment estimate for a stand to be used by the Experimental Weight Analysis Section. | 22th Jan 1940 | Box 143 \ 1 scan0389 | |
| Requesting the completion of drawings for the Fan and Water Pump Rig. | 23th Jan 1940 | Box 143 \ 1 scan0390 | |
| Internal memorandum requesting the purchase of typists' tables and a chair. | 25th Jan 1940 | Box 143 \ 1 scan0391 | |
| Chrome plating of cylinder bores as a solution to wear problems and the production of a new rig for the process. | 25th Jan 1940 | Box 143 \ 1 scan0392 | |
| The order of two Double Pedestal Typewriter Desks. | 26th Jan 1940 | Box 143 \ 1 scan0393 | |
| Ordering four chairs for Mr. Robotham's department at Park Leys. | 13th Feb 1940 | Box 143 \ 1 scan0394 | |
| Request to order one desk for the weight analysis section. | 21th Feb 1940 | Box 143 \ 1 scan0395 | |
| Request to order a standard type desk for the Weight Analysis Section. | 27th Feb 1940 | Box 143 \ 1 scan0396 | |
| Requesting temporary ventilation for the Experimental D.O. office at Clan Foundry. | 28th Feb 1940 | Box 143 \ 1 scan0397 | |
| Internal order confirmation for a typist's desk for the Suspension and Weight Section, Experimental Garage. | 2nd Mar 1940 | Box 143 \ 1 scan0398 | |
| Quotation for a variable speed gear and drive components for a chassis bumper rearrangement in the Experimental Department. | 14th Mar 1940 | Box 143 \ 1 scan0399 | |
| Specification sheet for Endless Sure Grip V Ropes for Messrs. Crofts (Engineers) Ltd. | 12th Mar 1940 | Box 143 \ 1 scan0400 | |
| Urgent internal memo requesting the supply of a wooden cabinet for storing experimental bearings. | 19th Mar 1940 | Box 143 \ 1 scan0401 | |
| Typed memo requesting Mr. Evingdon to sign and return a document. | 5th Apr 1940 | Box 143 \ 1 scan0402 | |
| Request for Tan-Sad chairs for the Experimental Department at the Clan Foundry. | 5th Apr 1940 | Box 143 \ 1 scan0403 | |
| Request form for replacement or additional equipment, specifically for Tan-Sad chairs for the Clan Foundry. | 5th Apr 1940 | Box 143 \ 1 scan0404 | |
| Memo regarding a new order, suggesting who should handle it and that the entire lot be ordered at once. | 8th Apr 1940 | Box 143 \ 1 scan0405 | |
| Internal order to proceed with making a test rig for conventional 8 distributors. | 6th Apr 1940 | Box 143 \ 1 scan0406 | |
| Requesting the installation of a luminous call system at the Clan Foundry. | 10th Apr 1940 | Box 143 \ 1 scan0407 | |
| Order memo to Messrs. Ferodo Ltd. for one Ferogrip Fan Belt for a Dynamo Test Rig. | 16th Apr 1940 | Box 143 \ 1 scan0408 | |
| Requesting an order for various sizes of rubber tubing for chassis unit test beds. | 10th May 1940 | Box 143 \ 1 scan0409 | |
| Requisition for one Fortin barometer for use on the Experimental chassis Test Beds. | 10th May 1940 | Box 143 \ 1 scan0410 | |
| Equipment estimate for the supply and fitting of a Gas Point to the spark plug bench in the Aero Electrical Laboratory. | 21th May 1940 | Box 143 \ 1 scan0411 | |
| State of fire fighting equipment at the Park Leys location. | 6th Jun 1940 | Box 143 \ 1 scan0412 | |
| The inadequacy of fire fighting equipment at the Park Leys Squash Court. | 9th Jun 1940 | Box 143 \ 1 scan0413 | |
| Internal requisition for an order of fire extinguishers and fire buckets for Park Leys. | 13th Jun 1940 | Box 143 \ 1 scan0414 | |
| Labelling, delivery, and guaranteed efficiency of fire extinguishers and buckets for 'Park Leys'. | 9th Jun 1940 | Box 143 \ 1 scan0415 | |
| Request to order three steel trestles with iron axle shafts and an additional nine axles. | 14th Jun 1940 | Box 143 \ 1 scan0416 | |
| Confirmation of a verbal order for 20 trolleys to WKS.1529 specification for the Clan Foundry, Belper. | 21th Jun 1940 | Box 143 \ 1 scan0417 | |
| File reference note regarding a thermostat for Clan Foundry. | 1st Oct 1940 | Box 143 \ 1 scan0418 | |
| Request for two draughtsmen's stands to be made from an attached sketch. | 8th Aug 1940 | Box 143 \ 1 scan0419 | |
| Requesting an oak chart cupboard with a roller shutter for an office at the Clan Foundry. | 4th Oct 1940 | Box 143 \ 1 scan0420 | |
| Request for Ford & Weston's to make two draughtsmen's tables for the full-size drawing of the Myth. | 6th Sep 1940 | Box 143 \ 1 scan0421 | |
| Follow-up request for drawing board covers and fittings. | 19th Oct 1940 | Box 143 \ 1 scan0422 | |
| Authorising the painting of the Clan Foundry exterior in a mat dull green. | 20th Oct 1940 | Box 143 \ 1 scan0423 | |
| Correcting a typing error in a previously quoted reference number. | 25th Oct 1940 | Box 143 \ 1 scan0424 | |
| Order to be placed for steel frames with castors. | 5th Nov 1940 | Box 143 \ 1 scan0425 | |
| Internal request to purchase electrical components for an electric clock in an office. | 6th Nov 1940 | Box 143 \ 1 scan0426 | |
| Urgent request to obtain a switch for a variable speed A.C. motor for a coolant pump. | 16th Nov 1940 | Box 143 \ 1 scan0427 | |
| Request to obtain an Elliot Microammeter for the Clan Foundry in Belper. | 27th Nov 1940 | Box 143 \ 1 scan0428 | |
| Urgent complaints about light escaping from a boiler house and missing security items for an air raid shelter and a passage door. | 17th Dec 1940 | Box 143 \ 1 scan0429 | |
| Incorrectly sized oil strainer and a request to order a replacement. | 22th Jan 1941 | Box 143 \ 1 scan0430 | |
| Responding to a query about parts in use at the Clan Foundry. | 20th Feb 1941 | Box 143 \ 1 scan0431 | |
| Chasing a reply regarding miscellaneous items supplied by Messrs. John Wallace to allow for invoice payment. | 7th Feb 1941 | Box 143 \ 1 scan0432 | |
| The delay in repairing a Pulsometer Pumping Set after its strainers were smashed by frost. | 25th Feb 1941 | Box 143 \ 1 scan0433 | |
| Confirming repair arrangements for a pulsometer pumping set and noting an inability to source strainers. | 24th Feb 1941 | Box 143 \ 1 scan0434 | |
| The order of two 1 1/2' three-way cocks for a coolant pump rig. | 13th Mar 1941 | Box 143 \ 1 scan0435 | |
| Request to despatch brake shoes and linings to New Hudson Ltd. for fitting and return. | 24th Apr 1941 | Box 143 \ 1 scan0436 | |
| Confirming the production of four more composite brake drums after a successful test of the first one. | 21th Apr 1941 | Box 143 \ 1 scan0437 | |
| Letter to New Hudson Ltd. regarding the dispatch and assembly of brake shoes and linings. | 19th Apr 1941 | Box 143 \ 1 scan0438 | |
| Letter to Messrs. New Hudson Ltd. regarding the despatch of brake shoes and linings for relining. | 24th Apr 1941 | Box 143 \ 1 scan0439 | |
| Requesting instructions for wiring a fan and desk light at the Clan Foundry offices. | 25th May 1941 | Box 143 \ 1 scan0440 | |
| Internal request to type a note asking for a cupboard to be made for storing body parts and accessories. | 28th Apr 1941 | Box 143 \ 1 scan0441 | |
| Requesting alterations at the Clan Foundry, specifically to erect a partition and provide a new door. | 7th May 1941 | Box 143 \ 1 scan0442 | |
| Requisition for a steel cupboard and a two-drawer card index cabinet from D.S. Butler Ltd. | 12th May 1941 | Box 143 \ 1 scan0443 | |
| Request to have a cupboard made for storing body parts and accessories at Clan Foundry. | 12th May 1941 | Box 143 \ 1 scan0444 | |
| Confirming the suitability of a metal cupboard with adjustable shelves for storing coachwork parts. | 21th May 1941 | Box 143 \ 1 scan0445 | |
| Fire risk due to enemy activity and requests for equipment to protect drawings stored at Park Leys. | 23th Nov 1940 | Box 143 \ 1 scan0446 | |
| Order confirmation to J. Thorp & Son Ltd. for the supply and erection of an unloading gantry for the Clan Foundry. | 6th Jun 1941 | Box 143 \ 1 scan0447 | |
| Order confirmation for a Yale Blue Streak Hand Lift Truck for the Clan Foundry. | 6th Jun 1941 | Box 143 \ 1 scan0448 | |
| Quotation for two types of 2-ton Yale foundry equipment, a trolley and a triple-geared chain block. | 6th Jun 1941 | Box 143 \ 1 scan0449 | |
| Requesting a window be fixed in a roof for ventilation due to excessive heat. | 16th Jun 1941 | Box 143 \ 1 scan0450 | |
| Equipment estimate for the manufacture and supply of rope slings for use at the Clan Foundry. | 16th Jun 1941 | Box 143 \ 1 scan0451 | |
| Chasing up issues with wiring heaters on a coolant pump rig and reporting missing parts from a recent order. | 26th Jun 1941 | Box 143 \ 1 scan0452 | |
| Potential sites and costs for a new dynamometer at Clan Foundry. | 3rd Jul 1941 | Box 143 \ 1 scan0453 | |
| Fire precautions at Clen, proposing a pressure feed system with an underground tank for lead petrol storage. | 3rd Jul 1941 | Box 143 \ 1 scan0454 | |
| Equipment estimate for a rig to check enrichment capsules on Merlin carburettors. | 11th Jul 1941 | Box 143 \ 1 scan0455 | |
| Equipment estimate to make and supply Vulture engine trestles for use at Clan Foundry, Belper. | 18th Jul 1941 | Box 143 \ 1 scan0456 | |
| The return of a Benson Stop Watch to the makers for repair. | 11th Aug 1941 | Box 143 \ 1 scan0457 | |
| Requesting the fitting of lights and lamps in the Test Bed Clan Foundry. | 12th Aug 1941 | Box 143 \ 1 scan0458 | |
| Urgent request for two Yale padlocks and one Yale lock for the Clan Foundry test bed. | 14th Aug 1941 | Box 143 \ 1 scan0459 | |
| Confirmation to create a drawing for a modified servo spring plate for a new snow sealing scheme. | 2nd Feb 1942 | Box 143 \ 1 scan0460 | |
| Order for oil resisting rubber rings from the British Tyre & Rubber Co., Ltd. | 2nd Feb 1942 | Box 143 \ 1 scan0461 | |
| Letter to Stainless Spinning Works confirming the manufacture of six modified phosphor bronze plate springs. | 3rd Feb 1942 | Box 143 \ 1 scan0462 | |
| Official order for 6 modified plate springs for experimental purposes. | 3rd Feb 1942 | Box 143 \ 1 scan0463 | |
| Record of a '10 Bv. car' loaned to Mr. J. Reid and returned to Clan Foundry. | 2nd Jul 1940 | Box 143 \ 2 scan0001 | |
| | | | |